Water department opens second Vaal Dam sluice gate
Ongoing: Gauteng water Hot

The Department of Water and Sanitation opened the second gate on Friday as the Vaal Dam stood at 113.25% of its full supply capacity. The first gate opened on Thursday 26 November, after strong inflows into the dam.
The department said the dam's water level was 23.540 metres. Inflows were 652.35 m³/s, and discharge from the dam was 151.910 m³/s. No rain was recorded, and evaporation was 6 millimetres.
The department said the high inflows came largely from recent rainfall in the upper catchment of the Vaal River System. It said the controlled release is meant to keep the downstream Bloemhof Dam at or below 90% of its full supply capacity. Maintenance work is under way on the upstream side of the Bloemhof Dam wall.
Both gates will stay open until further hydrological analysis decides what changes are needed, the department said. The statement named Vereeniging, Vanderbijlpark, Vaalpark and Parys among the places along the Vaal River.
Key facts
- Who
- Department of Water and Sanitation (department operating the Vaal Dam sluice gates and issuing the statement)
- What
- The Department of Water and Sanitation opened a second Vaal Dam sluice gate on Friday to manage rising water levels and substantial inflows, following the opening of the first gate on Thursday 26 November. Both gates will remain open until further hydrological analysis determines operational adjustments.
- When
- 27 November 2026
- Where
- Vaal Dam, Vaal River, Bloemhof Dam
- Status
- Reported